One deal, twelve weeks
Nothing here is dramatic. Each gap is small, and each one is paid for in hours.
An invented example, not a client and not a forecast. Hours are rounded; the day rate is $250 an hour.
| When | What happens | Hours lost |
|---|---|---|
| Thu | The deal closes at $90,000 fixed fee. A discount on extra work was agreed by email. The client is to supply its data by week 3. | 0 |
| Mon | Delivery rebuilds the job from the proposal, the scope notes and the email thread. Two people, a day each. | 16 |
| Week 3 | The client asks for one more report. The team builds it to keep the client happy. It is never logged as a change. | 30 |
| Week 5 | The client's data is late. The dependency was in the sales notes, not the delivery plan, so the plan is redone. | 12 |
| Week 8 | Finance asks which milestone triggers the invoice. Nobody is sure, and the answer takes a day to find. | 6 |
| Week 12 | The invoice goes out with a page of explanation. The client questions the extra report, and finance reworks it. | 10 |
74 hours nobody planned: $18,500 at $250 an hour, on a $90,000 job. No one made a mistake. The detail was never in one place.